Project Schedule

Schedule

Key milestones of the project are shown in the schedule below:

  • Public Open Houses – Winter 2021, Spring 2021, Summer 2022, Early Spring 2023
  • Preliminary Design – June 2020 to August 2021
  • Final Design – September 2021 to Jan 2023
  • Right of Way Acquisition Process – January 2022 to January 2023
  • Preliminary Construction Activities (Widening): Summer/Fall 2023
  • Primary Construction: Spring 2024 – Fall 2025

CSAH 56-57 Schedule 01-21-2022