Project Schedule
Below is an overview of the project schedule:
- Preliminary Design – Fall/Winter 2025
- Final Design – Summer/Fall 2026
- Construction – Summer 2027
Project Summary
Project Background / Description
This project consists of replacing the timber bridge on Bridgestone Road over Seelye Brook. Anoka County is working in partnership with the City of St. Francis.
Current Layout
Currently under Development
Project Updates
As of April 1, 2026
A single‑span prestressed concrete beam bridge has been selected as the bridge type; preliminary bridge plans were received at the end of February. A Phase 1a archaeological review has revealed concerns regarding a potential Indian burial mound in the project vicinity which will need further investigation. The 60% plans are expected in May.
Contact
If you have questions or would like to comment on the project, please contact the project representative below:
- Dan Frey, Design Engineer
Stay Updated!
For ongoing updates about this project and others in the area, visit the Construction Weekly. This newsletter is published each week during the construction season and provides details on current construction projects taking place on county roadways throughout Anoka County.
You can also subscribe to receive email notifications by using Notify Me.