Lake Drive at Kettle River Boulevard NE

Image of Lake Drive at Kettle River Boulevard.

Project Schedule

  • Preliminary Design - April 2025-July 2025 
  • Final Design - August 2025-September 2026
  • Construction - Spring 2027

Project Summary

Project Background/Description
This project involves the reconstruction of the intersection of Lake Drive NE (County Highway 23) and Kettle River Boulevard NE (County Highway 62). Planned improvements include the construction of a roundabout; closure of the access from 155th Avenue and Camp Three Road to Lake Drive; widening of Kettle River Boulevard to accommodate a northbound left-turn lane and a southbound right-turn lane; and associated drainage enhancements. Anoka County is working in partnership with the City of Columbus.


Public Engagement Events

Below is an overview of the open house event: 

  • Monday, July 14, 2025, 
    5:00 p.m. to 7:00 p.m.
    • Columbus City Hall
      16319 Kettle River Blvd NE
      Columbus, MN 55025

 

Project Updates

As of April 1, 2026
The 60% plans are expected in April. Right-of-way acquisition is underway for the two impacted parcels. The City of Columbus has agreed to allow a detour on Camp 3 Road. Traffic modeling is being performed to determine appropriate traffic control for the detour.


Current Layout

January 07, 2026


Contact 

If you have any questions or would like to comment on any aspect of the project, please contact the project representative below:

  • Michelle Pritchard, Design Engineer III