The Construction Weekly is published weekly during the construction season and includes details about current construction projects happening on Anoka County roadways. Check back weekly for updated construction information or, if you are interested in receiving email notifications of the updates, subscribe by using Notify Me.

As always,

Our Passion is Your Safe Way Home

2026 Construction Projects

Week Ending March 27, 2026


Mississippi Street (County Highway 6)

CSAH 6 (Mississippi St NE) from CSAH 1 (East River Road) to TH 47 (University Ave)
NO NEW UPDATE: Utility companies are in the process of relocating utilities; construction is tentatively scheduled to begin mid-May.


Rum River Boulevard (County Highway 7) 

CSAH 7 (Rum River Boulevard) at Seelye Brook - Bridge Replacement
THIS WEEK:  The contractor poured the north abutment barrel and wingwall section.   They continued to set forms and install steel reinforcements in the south abutment.  Lastly, they set forms and install steel reinforcements in the retaining wall footing.
NEXT WEEK:  The contractor will strip forms, backfill and install riprap at the north abutment.   They will pour the second half of the south abutment, backfill and install riprap at the south abutment.


Round Lake Blvd (County Highway 9)

CSAH 9 (Round Lake Blvd) from 100’ south of CSAH 116 (Bunker Lake Blvd) to 149th Lane
New signal lights at multiple locations in the corridor
THIS WEEK:  The electrical subcontractor is directional drilling conduit and installing temporary signal poles at various locations throughout the project.
NEXT WEEK:  Directional drilling will continue, new signal system handholes will be installed, and temporary signal poles will be installed at the intersection of Bunker Lake Boulevard & Round Lake Boulevard.


County Road 10 (County Highway 10)

CSAH 10 (County Road 10) from Able Street to the east County Line (Pleasant View Drive)
Bituminous and Concrete Pavement Removal and Bituminous Replacement
NO NEW UPDATE:  The contractor is scheduled to start work April 20, weather permitting.

 

Northdale Blvd (County Highway 11)

CSAH 11 (Northdale Blvd) at the intersection of Raven Street
Signal System Replacement and Safety Improvements
NO NEW UPDATE:  Construction is tentatively scheduled for early July

 

109th Avenue (CSAH 12)

CSAH 12 (109th Avenue) at the Intersection of CSAH 52 (Radisson Road)
Signal System Replacement and Safety Improvements
NO NEW UPDATE:  Construction is tentatively scheduled for late August

 

Main Street (County Highway 14)

CSAH 14 (Main Street) from TH 10 to CSAH 18 (Coon Creek Blvd)
Bituminous Removal & Replacement of the top 2 inches of bituminous
NO NEW UPDATE:  Construction is tentatively scheduled for early September

 

Crosstown Boulevard (County Highway 18)

CSAH 18 (Crosstown Blvd) at the Intersection of 161st Avenue / Constance Blvd
Intersection Improvements - Roundabout 
THIS WEEK: Tree removal was completed on March 27.
UPDATE:  Construction tentatively scheduled to begin mid-April.


Baugh Street (County Highway 22)

CSAH 22 (Baugh Street) from CR 64 (181st Avenue) to CSAH 22 (Viking Boulevard)
Reconstruction for Safety Improvements & Shoulder Widening
UPDATE:   The first stage of roadway construction, from 181st Avenue to 188th Avenue, is tentatively scheduled to begin on May 4.


85th Avenue (County Highway 32)

CSAH 32 (85th Avenue) at the intersection of CSAH 17 (Lexington Avenue) 
Signal system replacement and safety improvements
NO NEW UPDATE: Construction is tentatively scheduled for early September

 

County Road J & I-35E Interchange Project

For more information, see Ramsey County project website:
https://www.ramseycountymn.gov/residents/roads-transportation/current-road-projects/county-road-j-i-35e-interchange



2025 Construction Projects Scheduled for 2026 Completion

44th Avenue (County Highway 2)

CSAH 2 (44th Avenue NE) from CSAH 1 (East River Road) to CR 102 (Main Street) - Bridge Rehabilitation
NO NEW UPDATE: The bridge is open to traffic; minor work will continue in the spring of 2026.


Mississippi Street (County Highway 6)

CSAH 6 (Mississippi St NE) at 7th Street Intersection Improvements 
NO NEW UPDATE: Punchlist items will continue in the spring of 2026.


US Hwy 10/169 - Ramsey Gateway Project

US Hwy 10/169 at Ramsey Boulevard (County Highway 56) and Sunfish Lake Boulevard (County Highway 57) 
NO NEW UPDATE: Punchlist items will continue in the spring of 2026.
For more information, see the MnDOT project website: https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange

 

2026 County-Wide Pavement Preservation Program


CSAH 7 (7th Avenue) – 145th Avenue to 1130’ N of 165th Avenue
Road reclamation and new bituminous surface
UPDATE: Work has not been scheduled

CSAH 9 (Round Lake Blvd) – CSAH 116 (Bunker Lake Boulevard) to 149th Lane 
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CSAH 18 (Crosstown Blvd) – 1860’ W of TH 65 to 1540’ E of TH 65
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CSAH 32 (85th Avenue) – Rendova Street to 250’ E of CSAH 17 (Lexington Avenue)
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CSAH 36 (Rutgers Street) – North County line to CSAH 76 & (Fawn Lake Drive) CSAH 76 to East County line
Road reclamation and new bituminous surface
UPDATE: Work has not been scheduled

CSAH 52 (Lovell Rd) – Hamline Avenue to CSAH 17 (Lexington Avenue)
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CSAH 78 (Hanson Blvd) at Intersection with 155th Lane
Safety improvements by installing turn lanes to 155th Lane
UPDATE: Work is tentatively scheduled to begin in early June, once school is out for the summer, weather permitting.

CSAH 78 (Hanson Blvd) – 500’ S of CSAH 14 (Main Street) to Jay Street
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CR 86 (Sims Road NW) – University Avenue to 1300’ E of University Avenue
Soil correction and road surface replacement
UPDATE: Work is tentatively scheduled to begin in early June, once school is out for the summer, weather permitting.

CSAH 116 (Bunker Lake Blvd) – 600’ W to 1800’ E of Hanson Boulevard
Bituminous removal & replacement of the top 2 inches of bituminous, with spot drainage and curb replacement
UPDATE: Work has not been scheduled

CSAH 116 (Bunker Lake Blvd NW) – Lincoln Street to Johnson Street
Bituminous removal & replacement of the top 2 inches of bituminous